No. 27 - Confirmation of Operational Orbit
The remaining commissioning activities have been conducted according to the plan, with some activities rescheduling required. All the dedicated commissioning tests have now been concluded and the Case Commissioning phase is to start.
The table below shows a chronology of the main activities in the reporting period:
MET (Day) | Date | DOY | Main Activity |
178 | 05/05/06 | 125 | SC Monitoring |
179 | 06/05/06 | 126 | VeRA Commissioning #2 |
180 | 07/05/06 | 127 | Pericenter Control Manoeuvre #2 (3 ms-1) VeRA Commissioning #2 |
181 | 08/05/06 | 128 | VeRA Commissioning #3 |
182 | 09/05/06 | 129 | SPICAV Pointing #3 (Inertial Limb) |
183 | 10/05/06 | 130 | SPICAV Pointing #5 (Sun Pointing - fixed) |
184 | 11/05/06 | 131 | SPICAV Pointing #5 (Sun Pointing - scan) |
185 | 12/05/06 | 132 | SPICAV Pointing #3 (repeat Inertial Limb) SPICAV Pointing #4 (Solar occultation) |
186 | 13/05/06 | 133 | SC Monitoring and uplink Short Tem Planning 2 |
At the end of the last Cebreros pass in the reporting period (DOY 133, 14:00) Venus Express was orbiting Venus at 158 million km from the Earth. The one-way signal travel time was 527 seconds.
Spacecraft Status
AOCS
Manoeuvre |
Estimated ΔV |
Estimated Duration |
PCM #2 |
3.1014 |
301 |
On 7 May 2006, at 13:31:11.7 UTC Venus Express had its 17th apocenter passage and entered its first operational orbit. The achieved orbit has the following deviations from the nominal one:
- Period: + 0.3 seconds
- Inclination: 0.04°
- Apocenter: +1km
- Pericenter: -1km
This orbit will be maintained with routine orbit control manoeuvres, typically scheduled every 50 days.
Payload Activities
ASPERA
The instrument is currently OFF.
MAG
The instrument is ON in Solar Wind mode and science data are regularly downlinked.
PFS
The instrument is currently OFF.
SPICAV
The instrument has been activated for dedicated observations (SPICAV Obs#3, #4, #5, and #6). Science data are being analysed by the PI team.
VeRA
Dedicated New Norcia passes have been taken on DoY 125, 126, and 127 to complete the commissioning activities.
VIRTIS
The instrument is currently OFF.
VMC
The instrument is currently OFF.
Ground Facilities
During the reporting period Venus Express has been successfully supported by daily passes with Cebreros. On DoY 129 and 130 shorter passes have been taken to allow preventive maintenance activities to be conducted in the station.
Future Milestones
The Venus Orbit Commissioning Phase enters now the phase where the routine mission planning and operations scheme is phased-in. This foresees a weekly short term planning cycle governed by the operations requests submitted by the Science Operations Centre.
The first operational week is to start in Orbit#23 in the night between the 13 and 14 of May. Operations of the first week foresee the planning of the so called science cases which are the elementary science observations which will then compose the overall science activity plan. The 4200 commands required for the full week have been prepared during last week and the ones required to cover the first 4 days of operations are already on-board the spacecraft.
This first week of single observations will then be followed by two weeks where the single observations will be combined in a single orbit depending on the spacecraft thermal constraints. After 3 weeks of commissioning this scheme will be adopted as a standard to conduct the routine science phase which is to start on the 4th of June.
As from next reporting period this mission operations report will cover the period Sunday to Saturday to synchronise with the operational commanding period.