No. 4 - Platform Completes near Earth Commissioning; Payload Commissioning Underway

No. 4 - Platform Completes near Earth Commissioning; Payload Commissioning Underway

Report for period 11 November 2005 to 17 November 2005During the reporting period all the activities foreseen for the Near Earth Commissioning of theplatform have been conducted according to plan. The remaining testing activities on theplatform side will take place in January (thermal characterization) and in February (mainengine calibration).

The spacecraft behaviour has been nominal throughout the reporting period.

MET (Day)

Date

DOY

Main Activity

3

11/11/05

315

Ranging tests TRSP1 and TRSP2

4

12/11/05

316

Solar Arrays Flex mode characterization

5

13/11/05

317

SC Inertial calibration

6

14/11/05

318

STRs Alignment Testing

7

15/11/05

319

Disturbance Torques Calibration and HGA1 RF test

8

16/11/05

320

HGA2 Pattern Calibration

9

17/11/05

321

AOCS Configuration for NECP

At the end of the last Cebreros pass in the reporting period (DOY 321, 21:00) Venus Express was at 2.25 million km from Earth, 147 million km from the Sun, and 81.5 million km from Venus. The one-way signal travel time was 7.5 seconds.

Upcoming Activities

  • Payload Commissioning will start for MAG, VIRTIS, and VMC
  • During this period the Earth-Moon observation is planned
Last Update: 1 September 2019
24-Apr-2024 16:28 UT

ShortUrl Portlet

Shortcut URL

https://sci.esa.int/s/wxlzYyw

Images And Videos

Related Publications

Related Links

See Also

Documentation