No. 68 - Mission Latest
The table below shows a chronology of the main activities in the reporting period:
MET (Day) | Date | DOY | VPER# | Main Activity |
474 | 25/02/07 | 056 | 310 | Routine Mission Operations |
475 | 26/02/07 | 057 | 311 | Routine Mission Operations |
476 | 27/02/07 | 058 | 312 | Routine Mission Operations |
477 | 28/02/07 | 059 | 313 | Routine Mission Operations |
478 | 01/03/07 | 060 | 314 | Routine Mission Operations |
479 | 02/03/07 | 061 | 315 | Routine Mission Operations |
480 | 03/03/07 | 062 | 316 | Routine Mission Operations TM information bit rate increased to 114kbps after pass. |
At the end of the last Cebreros pass in the reporting period (DOY 062, 18:00z) Venus Express was orbiting Venus at 207 million km from the Earth. The one-way signal travel time was 690 seconds.
Payload Activities
ASPERA
The instrument is regularly operated as part of the routine plan.
MAG
The instrument is regularly operated as part of the routine plan.
PFS
This instrument is OFF and is not operated.
SPICAV
The instrument is regularly operated as part of the routine plan.
VeRa
Nothing to report.
VIRTIS
Nominal operation of VIRTIS continue.
VMC
Other than a small data anomaly the instrument continued being regularly operated as part of the routine plan.
Future Milestones
VIRTIS movie passes are scheduled for the second week of April (DOY 98-101). Planning of science operations during this event is now finished. The testing of operations during quadrature is on-going; the next quadrature phase will start in May 2007.