No. 206 - Orbit control manoeuvres

No. 206 - Orbit control manoeuvres

Report for Period 18 October to 24 October 2009The Venus Express spacecraft and instruments performed nominally during this week. Two orbit control manoeuvres were successfully performed; one to lower the orbit's apocentre altitude and one to raise the pericentre altitude. On DOY 293 the regular DDOR measurements were performed.

Orbit control manoeuvres
The orbit of Venus Express slowly evolves due to natural perturbations. The pericentre altitude is kept within the allowed range by orbit control manoeuvres (OCM) performed at specific times. At the end of the previous reporting period the Venus Express spacecraft reached the currently set lower limit of 175 km for the altitude of the pericentre passage. Two OCMs were therefore performed at the beginning of this reporting period.

On 18 October an OCM was first performed to lower the orbit's apocentre altitude. This was followed by an OCM on 19 October to raise again the pericentre altitude. Both the OCMs were successful and performed nominally.

DDOR
On 20 October delta differential one-way ranging (DDOR) was performed using the New Norcia and Cebreros ground stations to track the spacecraft. These measurements are performed monthly to support the accurate determination of the ephemeris for the planet Venus that is maintained by NASA's Solar System Dynamics Group.

The DDOR measurement principle uses a technique to highly accurately determine the position of a transmitter in space and relies on observing the time delay between reception of the signal from the transmitter by two ground stations at different positions on Earth. In this case the Venus Express spacecraft is the transmitter and the two ground stations are New Norcia in western Australia and Cebreros in Avila, Spain.

The table below shows a chronology of the main activities:

MET
(Day)
Date DOY Main Activity
1440 18/10/09 291

Communications pass over Cebreros.
Apocentre lowering manoeuvre

1441 19/10/09 292

Communications pass over Cebreros.
Pericentre raising manoeuvre

1442 20/10/09 293

Communications pass over Cebreros.
DDOR with Cebreros and New Norcia

1443 21/10/09 294

Communications pass over Cebreros

1444 22/10/09 295

Communications pass over Cebreros

1445 23/10/09 296

Communications pass over Cebreros

1446 24/10/09 297

Communications pass over Cebreros

At the end of the last Cebreros pass in the reporting period (DOY 297) Venus Express was orbiting Venus at 236 million km from the Earth. The one-way signal travel time was 787 seconds.

Payload Activities

ASPERA
The instrument was regularly operated as part of the routine plan.

MAG
The instrument was regularly operated as part of the routine plan.

PFS
The instrument was not operated during the reporting period.

SPICAV
The instrument was regularly operated as part of the routine plan.

VeRA
No radio science observations were made during the reporting period.

VIRTIS
VIRTIS-M was operated in the visual channels only.

VMC
The instrument was regularly operated as part of the routine plan.


Future Milestones

  • Superior conjunction: 29 December 2009 to 22 January 2010


---
Legal disclaimer
This report is based on the ESOC mission operations report, MOR #206. Please see the copyright section of the legal disclaimer (bottom of this page) for terms of use.

Last Update: 1 September 2019
26-Apr-2024 20:47 UT

ShortUrl Portlet

Shortcut URL

https://sci.esa.int/s/w05g7zW

Images And Videos

Related Publications

Related Links

See Also

Documentation