Status report archive

Status report archive

Report for Period 8 October to 14 October 2006The reporting period contained a spacecraft hardware safe mode which occurred on DoY 282 04:20 UT.
Published: 20 October 2006
Report for Period 1 October to 7 October 2006During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal.
Published: 10 October 2006
Report for Period 24 September to 30 September 2006The reporting period contained a spacecraft hardware safe which occurred on 27 September (DoY 270) at 04.37 UT.
Published: 6 October 2006
Report for Period 17 September to 23 September 2006The reporting period contained a spacecraft hardware safe which occurred on 22 September (DoY 265) at 19:24 UT.
Published: 28 September 2006
Report for Period 10 September to 16 September 2006During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal.
Published: 19 September 2006
Report for Period 3 September to 9 September 2006During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal.
Published: 18 September 2006
Report for Period 27 August to 2 September 2006During the reporting period the mission operations have been conducted according to the plan.The ground and the space segment performance have been nominal.
Published: 3 September 2006
Report for Period 20 to 26 August 2006The reporting period contained a spacecraft hardware safe which occurred on DoY 237 at 18:15 UT. The outage has caused the following impact at mission level: science operations from Safe Mode occurrence until spacecraft recovery to nominal operations (238 11.48) have been skippedUSO switched OFF for about 16...
Published: 30 August 2006
Report for Period 13 August to 19 August 2006During the reporting period the Venus Express mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal.
Published: 22 August 2006
Report for Period 6 August to 12 August 2006During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal.
Published: 15 August 2006
During the reporting period the mission operations have been conducted according to the plan. Theground and the space segment performance have been nominal.
Published: 8 August 2006
Report for Period 23 July to 29 July 2006During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominal with the exception of a few telemetry outages at the ground station due to a loss of lock.
Published: 2 August 2006
Report for Period 16 July to 22 July 2006 During the reporting period the mission operations have been conducted according to the plan. The ground and the space segment performance have been nominally with the exception of a few Telemetry outages at the Ground Station due to thunder storms and lightning.
Published: 24 July 2006
Report for Period 9 July to 15 July 2006 During the reporting period the mission operations have been conducted according to plan. The spacecraft performance was nominal throughout the reporting period and several outstanding system level operations have been performed.
Published: 16 July 2006
Report for Period 2 July to 8 July 2006During the reporting period the mission operations have been conducted according to plan. The ground and the space segment performance have been nominal with the exception of the mission data system. The Mission Control System (MCS) problems raised by the integration of the latest version have now been...
Published: 12 July 2006
Report for Period 25 June to 1 July 2006 During the reporting period the mission operations have been conducted according to the plan.The ground and the space segment performance have been nominal.
Published: 3 July 2006
Report for Period 18 June to 24 June 2006During the reporting period the mission operations have been conducted according to the plan. Minor problems with the ground station and with the new Mission Control System have slightly affected the operations.
Published: 26 June 2006
Report for Period 11 June to 17 June 2006During the reporting period, Venus Express experienced its first Safe Mode since launch. This occured on 12 June, DoY 163, at the end of a data recovery action due to a ground station problem on DoY 162.
Published: 20 June 2006
Report for Period 04 June to 10 June 2006All activities of Venus Express's first week of the routine phase have been executed as planned without any problem. The performance of the space and the ground segment has been nominal during the reporting period. The planning cycle proceeds in its activities and according to the plan.
Published: 12 June 2006
Report for Period 28 May to 03 June 2006On 3 June at 13:42 UT, after 207 days of flight, 43 orbits around Venus and many test activities, Venus Express has formally completed its commissioning phase and has entered the routine science phase. This will be formalised only with the Mission Commissioning Results Review to be held end of June. The...
Published: 6 June 2006
14-Dec-2024 13:11 UT

ShortUrl Portlet

Shortcut URL

https://sci.esa.int/p/gAjBxxA