No. 70 - First Payload Active Checkout Operations

No. 70 - First Payload Active Checkout Operations

Report for Period 1 December to 8 December 2006The reporting period covers one week of active cruise, which was dedicated to instrument Active Checkout operations.

During the reporting period, the two navigation cameras and all instruments were operated with the exception of MIDAS, MIRO, ROSINA and VIRTIS. In particular, interactive checkout operations were performed with COSIMA, the Lander Philae and OSIRIS. On 6 December, the RPC (Rosetta Plasma Consortium) IES Noisy Channel test, which had failed on 26 November, was successfully repeated. RPC and SREM remain active in the background throughout the campaign. The other instruments are only activated for their checkout sequences.

All checkout operations during the reporting period have been executed smoothly, with the exception of one ALICE command and one failed GIADA command on 4 December, which led to the cancellation of a GIADA observation scheduled on 11 December. The command failures have had no impact on the instrument safety.

In addition, during execution of checkout operations on 1/2 December, telemetry generation by the Lander MUPUS instrument was suddenly and unexpectedly interrupted. Trouble-shooting activities were performed in the following passes. It was decided to leave MUPUS OFF until the nature of the problem is better understood.

A total of 5 New Norcia (NNO) passes of 9 to 12 hours commanding were taken during the reporting period. Two tracking passes of 4 hours have been taken with DSN.

NNO
Pass
Date DOY Main Activity
1007 01.12.06 335 COSIMA PC4 - pass 1 + Lander monitoring
1010 04.12.06 338 PC4 Data Dump
1011 05.12.06 339 Lander PC4 - pass 4 + RPC Files Uplink
1012 06.12.06 340 Lander PC4 - pass 5
1013 07.12.06 341 OSIRIS PC4 - pass 1 + Lander monitoring

At the end of the reporting period (DOY 342) Rosetta was at 301.1 million km from Earth (2.01 AU; one-way signal travel time was 16 min 5 sec). The distance to the Sun was 168 million km (1.12 AU).

Spacecraft

Payload
The reporting period included one interactive pass dedicated to COSIMA operations on DOY 335/336, the second non-interactive PC4 block between DOY 336 and 338, and four interactive passes dedicated to Lander and OSIRIS operations between DOY 338 and 342.

The second PC4 non-interactive block executed outside ground station coverage and involved ALICE, COSIMA, GIADA, OSIRIS, RPC and SREM. The data acquired during this block were retrieved by the ground station on DOY 338. All operations scheduled during this block had executed nominally, with the exception of one ALICE and one GIADA command.

COSIMA
Interactive COSIMA operations were carried out on DOY 335/336. This included Emitter A tests and COSISCOPE software update and validation. All activities were successful.

OSIRIS
The reporting period included one interactive pass dedicated to OSIRIS operations on DOY 341/342. During this pass, the OSIRIS on-board software was completely replaced by software release 2.0. The activity was successful. Validation of the on-board software is scheduled on DOY 342/343.

Lander Philae
During the reporting period, the following interactive payload checkout operations were performed on the Lander Philae:

Instrument DOY 335/336 DOY 339/340 DOY 340/341
APXS

-

-

-

CIVA CIVA/P exposure test CIVA-M/SD2 combined operations and heating of the inner compartment for ADS

-

CONSERT CONSERT-Lander verification; Ping-pong test

-

-

COSAC Oven test

-

-

MUPUS

-

-

-

Ptolemy MS conditioning part 2 MS test 1, 2, 3 and 4 IT table2 upload; MS test 4 repeated
ROLIS

-

-

-

ROMAP

-

SPM HV1 and HV2 ROMAP/RPC joint observation
SD2

-

-

-

SESAME CFT2 repetition; EEPROM refresh

-

CASSE calibration

In addition, on DOY 341/342, a SESAME vibration test was carried out, and a SESAME WOL measurement was made.

At the end of the reporting period, the Lander remains ON. The operations are planned to complete late on DOY 342.

Future Milestones

The Mars Swingby Phase formally started on 28 July. The actual swingby will take place on 25 February 2007, followed by a Deep Space Manoeuvre in April 2007.

The on-going Payload Active Checkout (PC4) will last four weeks, with the last operations scheduled to be completed on 22 December. The next short-term activities include a thermal characterisation on 27 December, an observation of asteroid Lutetia by OSIRIS between 2 and 4 January 2007, and a test of the pre-eclipse Mars observation attitude on 7 January.

Last Update: 1 September 2019
29-Mar-2024 14:16 UT

ShortUrl Portlet

Shortcut URL

https://sci.esa.int/s/A2K6LPw

Images And Videos

Related Publications

Related Links

See Also

Documentation

Further Readings