Asset Publisher

Activities resume in Kourou

Activities resume in Kourou

17 September 2003

Final assembly facility, Kourou, French Guiana

In the past few days preparational work has resumed on SMART-1 in anticipation of a launch in the next couple of weeks. Since the Project Team reassembled in Kourou over the previous weekend the following activities have been and will be carried out.

16 September - Readiness review
17 September

- Moving SMART-1 from BAF-HE to Airlock
- SMART-1 mating onto launch vehicle
- Grounding check

18 September - SMART-1 final inspection
19 September

- Final checks
- Moving SMART-1 from BAF to the
  S5 Storage Area

Last Update: 1 September 2019
27-Apr-2024 03:11 UT

ShortUrl Portlet

Shortcut URL

https://sci.esa.int/s/wKe9jP8

Images And Videos

Related Publications

Related Links

Documentation