Activities resume in Kourou
17 September 2003
Final assembly facility, Kourou, French GuianaIn the past few days preparational work has resumed on SMART-1 in anticipation of a launch in the next couple of weeks. Since the Project Team reassembled in Kourou over the previous weekend the following activities have been and will be carried out.
16 September | - Readiness review |
17 September |
- Moving SMART-1 from BAF-HE to Airlock |
18 September | - SMART-1 final inspection |
19 September |
- Final checks |